N | Объект | Ста- | ГП | ТХ | АВТ | ЭО | Элект Защ | Газ | АСЧ | ВК | ОВ | Пас Защ | ПОС | Смет |
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 16 | 17 |
1 | Газоборудование потребителей | П | - | - | 10,0 | - | - | 72,0 | - | - | - | - | 8,0 | 10,0 |
без ГРУ | Р | - | - | 15,0 | - | - | 85,0 | - | - | - | - | - | - | |
РП | - | - | 10,0 | - | - | 75,0 | - | - | - | - | 5,0 | 10,0 | ||
2 | Внутрицеховое ГРУ с регулятором | П | - | - | 10,0 | - | - | 72,0 | - | - | - | - | 8,0 | 10,0 |
Р | - | - | 15,0 | - | - | 85,0 | - | - | - | - | - | - | ||
РП | - | - | 10,0 | - | - | 75,0 | - | - | - | - | 5,0 | 10,0 | ||
3 | ГРП шкафного типа (ШРП), привязка | П | 10,0 | - | - | - | - | 74,0 | - | - | - | - | 6,0 | 10,0 |
Р | 10,0 | - | - | - | - | 90,0 | - | - | - | - | - | - | ||
РП | 10,0 | - | - | - | - | 74,0 | - | - | - | - | 6,0 | 10,0 | ||
4 | ГРП с регулятором | П | 3,0 | - | 13,0 | 2,0 | - | 32,0 | 24,0 | - | 8,0 | - | 8,0 | 10,0 |
Р | 2,0 | - | 9,0 | 5,0 | - | 42,0 | 36,0 | - | 6,0 | - | - | - | ||
РП | 3,0 | - | 11,0 | 6,0 | - | 29,0 | 26,0 | - | 9,0 | - | 6,0 | 10,0 | ||
5 | КРП, ГРС | П | 3,0 | - | 11,0 | 4,0 | - | 28,0 | 27,0 | 4,0 | 8,0 | - | 5,0 | 10,0 |
Р | 4,0 | - | 12,0 | 5,0 | - | 39,0 | 30,0 | 4,0 | 6,0 | - | - | - | ||
РП | 3,0 | - | 12,0 | 6,0 | - | 24,0 | 26,0 | 4,0 | 9,0 | - | 6,0 | 10,0 | ||
6 | Резервно- | П | 3,8 | - | 16,7 | - | - | 41,0 | 15,4 | - | - | - | 10,3 | 12,8 |
устройство (РРУ) | Р | 2,8 | - | 12,6 | - | - | 58,8 | 25,8 | - | - | - | - | - | |
РП | 4,2 | - | 15,0 | - | - | 41,0 | 19,0 | - | - | - | 8,0 | 12,8 | ||
7 | АИТ | П | 26,0 | 9,0 | 5,0 | - | 10,0 | 25,0 | 3,0 | 6,0 | - | 6,0 | 10,0 | |
Р | 28,0 | 10,0 | 5,0 | - | 20,0 | 29,0 | 3,0 | 5,0 | - | - | - | |||
РП | - | 26,0 | 10,0 | 5,0 | - | 10,0 | 25,0 | 2,0 | 6,0 | - | 6,0 | 10,0 | ||
8 | Металлические | П | - | - | - | - | - | - | 84,0 | - | - | - | 6,0 | 10,0 |
для АИТ | Р | - | - | - | - | - | 100,0 | - | - | - | - | - | ||
РП | - | - | - | - | - | - | 84,0 | - | - | - | 6,0 | 10,0 | ||
9 | АИТ для теплоснабжения одноквартирного | П | - | 27,0 | 10,0 | 4,0 | - | 24,0 | 10,0 | 4,0 | 7,0 | - | 4,0 | 10,0 |
или блокированного жилого здания, | Р | - | 27,0 | 10,0 | 5,0 | - | 23,0 | 20,0 | 4,0 | 7,0 | - | 4,0 | - | |
производственного здания | РП | - | 23,0 | 13,0 | 4,0 | - | 24,0 | 10,0 | 4,0 | 8,0 | - | 4,0 | 10,0 | |
10 | Газовый колодец | П | - | - | - | - | - | 10,0 | 75,0 | - | - | - | 5,0 | 10,0 |
Р | - | - | - | - | - | 10,0 | 90,0 | - | - | - | - | - | ||
РП | - | - | - | - | - | 10,0 | 75,0 | - | - | - | 5,0 | 10,0 | ||
11 | Крановый узел | РП | 6,0 | - | 10,0 | - | - | 35,0 | 32,0 | - | - | - | 7,0 | 10,0 |
12 | Станция регазификации | П | 2,5 | 35,0 | 8,0 | 2,0 | - | - | 24,0 | 3,0 | 6,5 | 1,0 | 8,0 | 10,0 |
Р | 2,5 | 32,5 | 11,0 | 4,0 | - | - | 40,0 | 3,0 | 6,0 | 1,0 | - | |||
РП | 2,5 | 31,5 | 11,0 | 4,0 | - | - | 26,0 | 2,0 | 6,0 | 1,0 | 6,0 | 10,0 | ||
13 | Автомобильная газозаправочная | П | 2,0 | 30,0 | 7,0 | 3,5 | - | - | 29,0 | 3,0 | 6,5 | 1,0 | 8,0 | 10,0 |
станция | Р | 2,5 | 32,0 | 11,0 | 3,0 | - | - | 42,0 | 2,5 | 6,0 | 1,0 | - | - | |
РП | 2,0 | 30,0 | 10,0 | 3,0 | - | - | 29,0 | 3,0 | 6,0 | 1,0 | 6,0 | 10,0 | ||
14 | Резервуарная установка | П | 2,0 | 34,5 | 6,0 | 5,5 | - | - | 27,0 | - | 6,0 | 3,0 | 8,0 | 10,0 |
Р | 3,0 | 40,0 | 9,0 | 6,0 | - | - | 35,0 | - | 6,0 | 1,0 | - | - | ||
РП | 2,0 | 32,5 | 8,0 | 5,5 | - | - | 27,0 | - | 6,0 | 1,0 | 8,0 | 10,0 | ||
15 | Электрозащитная установка от | П | - | - | - | - | 80 | - | - | - | - | - | 10,0 | 10,0 |
коррозии (катодная, | Р | - | - | - | - | 100,0 | - | - | - | - | - | - | - | |
электродренажная) | РП | - | - | - | - | 80 | - | - | - | - | - | 10,0 | 10,0 | |
16 | Молниезащита ГРП, ГРС | П | - | - | - | 75,0 | - | - | 10,0 | - | - | - | 5,0 | 10,0 |
Р | - | - | - | 100 | - | - | - | - | - | - | - | - | ||
РП | - | - | - | 84,0 | - | - | - | - | - | - | 6,0 | 10,0 |